PROJECT/EQUIPMENT

LOCAL FUNDING

OTHER  FUNDING

STATUS

GOLF:

 

 

 

     Irrigation Well

$320,000

 

$72K Oblig.to PW

     Safety Netting

$28,000

 

In procurement

     Golf Course Green Tees

$50,000

 

Option for GC complex upgrade

     Range Ball Machine & Building

$12,000

 

In progress

     Golf Carts

$120,000

 

$113K Obligated

     Greensmower

$33,000

 

$23K Obligated

     Self Help Cart Paths

$165,000

 

 

     Utility Vehicle

$15,000

 

 

     Bunker Sand

$15,000

 

 

     Golf Course Complex Upgrade

$50,000

 

RFP Technical Review Mtg. March 1,  In Contracting

     Lake Project

$33,000

 

In progress

     Golf Course Complex Upgrade

 

NAFCON

Start Est. 2001

     Golf Course Irrigation System

 

NAFCON

Working on project submission for funding consideration

RV CAMPGROUND:

 

 

 

     RV Campground Concrete Slabs

$70,000

 

$70K Oblig.to PW

     RV Campground Equipment

$33,180

 

$28K Obligated

     RV automatic gate/safety net

$68,000

 

$68K Oblig.to PW

CLUB:

 

 

 

     Design for Club Areas

$90,000

 

$83K Oblig.to PW

     Club Renovation Collateral

$200,000

 

 

     Club Del Monte Renovation

$450,000

 

In design

INFO., TICKETS & TOURS:

 

 

 

     ITT Renovation

$70,000

 

On hold pending NPS plan

YOUTH CENTER:

 

 

 

     New Facility

 

NAFCON

Est. Jun 01, In construction 98% Complete

     Youth Ctr. NAFCON start up

$50,000

 

$25K Obligated

     Youth Multipupose Field

 

NPC O&MN

FY03

GYM:

 

 

 

     New Facility

 

MILCON

Est. 2001, Project Start 2 Oct 00

     Collaterial Equipment

 

Unfunded

$508K Total.  $300K Funded by PERS-65, $208K unfunded

BUSINESS SUPPORT OFFICE:

 

 

 

     Marketing Renovations

$10,000

 

On hold pending NPS plan

ALL ACTIVITIES:

 

 

 

     MWR Signage

$60,000

 

$6K Obligated

     Point of Sale System

$130,000

 

Waiting for BUPERS MIS system

     Computer Upgrade

$13,000

 

$4K Obligated